Cost authority and approval matrix
Overruns often begin with someone on site agreeing an extra that nobody with budget authority ever saw. A one-page matrix saying who may instruct a change, who may commit spend at each value band and who signs off contingency closes that gap before the first instruction is issued.
First tasks
- List everyone who currently gives instructions on site or by email
- Check which roles the building contract allows to issue instructions
- Set value bands and an approver for each band
- Issue the matrix and ask each party to confirm receipt
- Recheck the matrix against current staff and roles @recurring(quarterly)