Each project arrives with its purpose, milestones and first tasks written out. Here is how the first three read.
Estimate classes and expected accuracy ranges
Engineers are often asked for a number without anyone saying how good it needs to be, and a concept guess ends up quoted as if it were a firm price. Learning the five-class system used across the process industries, from Class 5 screening to Class 1 check estimates, lets you match the method and the effort to the maturity of the scope and say out loud how wide the range is.
First tasks
- Find the estimate classification guidance your organisation or client uses
- Summarise the five classes with scope maturity, method and range on one page
- Label each estimate you own with its class and accuracy range
- Draft a standard accuracy sentence for estimate cover sheets
Basis of estimate document
Six months after an estimate is issued, nobody remembers which drawings revision it priced, which rates it used or what it left out, and the number is defended from memory. A basis of estimate written alongside the workbook records scope, sources, methods, assumptions, exclusions and allowances, so a reviewer can follow every figure and the next revision starts from facts.
First tasks
- Copy a section outline for a basis of estimate into a new document
- List every drawing and datasheet revision the estimate priced
- Write the exclusions list and read it as a sceptical client would
- Issue the basis under the same revision as the estimate workbook
Cost breakdown structure and code of accounts
Estimates that are coded differently from the way the project will collect actuals can never be compared afterwards, and benchmarking becomes guesswork. Setting a code of accounts that splits cost by area, discipline and commodity, and agreeing it with project controls before pricing starts, means the estimate becomes the control budget and closed projects feed the database cleanly.
First tasks
- Ask project controls how actual costs will be coded on this project
- Draft area, discipline and commodity levels for the code of accounts
- Run a filter in the workbook for lines with no cost code
- Save the agreed structure in the shared estimating folder