FEED Studies

A FEED that holds up at final investment decision: a frozen basis of design, defined process and layout, controlled holds and changes, a defensible estimate basis and a clean handover to the EPC contractor.

Free · Mac (Apple silicon) and Windows · v1.0.5 · Other platforms

Then open the Marketplace in the app, search for FEED Studies, and click Install. It goes into your own files, and works offline from then on.

Before you start: this plan is general information to help your team organise its work. It does not replace professional judgement, the rules of your regulator or professional body, your organisation's policies, or advice from a qualified lawyer, accountant or other adviser. Where a law, code or standard applies, use the current official version for your country, and get qualified sign-off on regulated or safety-critical work.

What it installs.

1

Pillar

1

Area

50

Projects

200

Starter tasks

🔧 Engineering Practice

FEED Studies

Delivering front-end engineering design: basis of design, process and layout definition, equipment lists, cost estimates and the package behind a final investment decision.

  1. Where FEED sits between concept select and FID
  2. FEED scope of work and contract read-through
  3. Basis of design document
  4. Site conditions and feed data sheet
  5. FEED deliverables register by discipline
  6. Project codes, standards and specifications list
  7. Concept select report handover review
  8. FEED kick-off and responsibility matrix
  9. FEED execution plan and schedule to FID
  10. Weekly FEED progress measurement
  11. Technical query log with the client and licensors
  12. Holds and assumptions register
  13. Weekly interface meeting with licensors and the owner
  14. FEED change notices and scope trend control
  15. FEED risk and opportunity register
  16. FEED lessons learned register
  17. Monthly FEED report to the owner
  18. Inter-discipline check cycle for FEED deliverables
  19. Reading PFDs and heat and material balances
  20. Equipment list to FEED definition
  21. Plot plan and layout principles for FEED
  22. Line sizing and hydraulics at FEED accuracy
  23. Datasheets and requisitions for major equipment
  24. Material take-offs for the FEED estimate
  25. Utility balance and tie-in list
  26. Electrical load list and power supply concept
  27. Operating, control and safety philosophies
  28. Long-lead equipment and early procurement decision
  29. Process technology licensor selection
  30. Modular versus stick-built construction decision
  31. FEED value engineering workshop
  32. Design margins and overdesign review
  33. Construction and logistics strategy input
  34. Site surveys, geotechnical and as-built verification
  35. Environmental and permitting inputs to FEED
  36. Safety studies schedule across the FEED
  37. Basis of design freeze and sign-off
  38. Independent technical assurance review before FID
  39. FID package and decision support
  40. EPC invitation to tender package from the FEED
  41. FEED close-out and handover to EPC
  42. Your first FEED as a graduate discipline engineer
  43. Owner's engineer overseeing a FEED contractor
  44. Lean brownfield FEED for a local engineering firm
  45. Discipline lead on a FEED contractor team
  46. Moving from operations into a FEED team
  47. Dual FEED competition and conversion to EPC
  48. Front-end loading index self-assessment
  49. Weight and space control for offshore FEED
  50. Replicating a FEED from a sister plant

Where it starts.

Each project arrives with its purpose, milestones and first tasks written out. Here is how the first three read.

Where FEED sits between concept select and FID

Engineers often join a FEED without knowing what the previous stage decided or what the next gate expects, so they rework settled questions and miss the ones the investment committee will ask.

First tasks

  • Ask the project manager for the owner's stage gate procedure
  • Draw the gates on one page with the decision made at each
  • List the concept select decisions and where each is recorded
  • Write the FID gate requirements as a checklist for the team

FEED scope of work and contract read-through

Most FEED disputes trace back to a scope of work nobody read line by line: a missing tie-in, an unpriced survey, a licensor package assumed to be someone else's. Reading the FEED contract, scope of work and deliverables schedule against each other in the first two weeks, and raising every gap as a clarification, sets the boundary before the hours are spent.

First tasks

  • Collect the FEED contract, scope of work and deliverables schedule
  • Mark every scope item that has no matching deliverable
  • Write the gap list with a proposed interpretation for each
  • Send the gap list to the client as formal clarifications

Basis of design document

Every discipline designs against one document, the basis of design, which sets capacity, turndown, feed and product specifications, design life, availability target, utility conditions and the governing codes. Writing it early, issuing it for client approval and putting it under revision control stops each discipline from inventing its own assumptions.

First tasks

  • Gather the concept select report, owner standards and licensor data
  • Draft the basis sections for capacity, feeds, products and design life
  • Mark every untraced value as an assumption with a named owner
  • Issue the basis for client comment and log the responses

Make it yours.

Install FEED Studies, then tell Aurum the date you're aiming for. It checks whether the plan fits the weeks you actually have.