Each project arrives with its purpose, milestones and first tasks written out. Here is how the first three read.
HAZOP method grounding from IEC 61882
People sit in HAZOPs for years without reading how the method is meant to work, and it shows in vague deviations and safeguards that are really just hopes. Working through the application guide in IEC 61882 and the hazard evaluation guidance from CCPS gives you the shared vocabulary of nodes, design intent, guidewords, parameters, deviations, causes, consequences and safeguards that every later project relies on.
First tasks
- Find the current editions of IEC 61882 and your company HAZOP procedure
- Write a one-page summary of the study stages from definition to follow-up
- Build a glossary of twelve HAZOP terms with a plant example for each
- Book thirty minutes with the process safety lead to ask your three questions
Study terms of reference and scope boundary
Arguments in week two of a HAZOP about whether the flare header or the vendor skid is in scope cost days and goodwill. A signed terms of reference fixes the scope boundary, the drawing revisions, the design stage, the risk matrix, the recording method and who approves the report before anyone opens a P&ID in the room.
First tasks
- Ask the project lead for the latest PFD and the list of P&IDs in scope
- Mark the scope boundary and every tie-in on one overall drawing
- Draft the terms of reference covering scope, exclusions, team and approval
- Get the sponsor and the HAZOP leader to sign the final terms of reference
Node breakdown on a marked-up P&ID set
Nodes that are too big hide deviations, and nodes that are too small turn a two-week study into six. Dividing the P&IDs into nodes by design intent, usually at changes of pressure, phase, composition or function, and colouring them on a controlled set gives the team a map they can follow and the scribe a reference for every row.
First tasks
- Print or open a controlled copy of every in-scope P&ID at the frozen revision
- Draw node boundaries at changes of pressure, phase or function
- Write a node list with drawings, boundaries and equipment for each node
- Walk the node list through with the process engineer and fix any gaps