Each project arrives with its purpose, milestones and first tasks written out. Here is how the first three read.
Work order lifecycle and status definitions
Most sites have a CMMS full of work orders stuck in statuses nobody can define, so backlog reports mix jobs waiting for parts with jobs nobody has looked at. Writing down eight or so statuses, from requested through approved, planned, ready, scheduled, in progress, complete and closed, with who moves a job between each, gives every later report a meaning.
First tasks
- Export open work orders and count them by current status
- Draft a definition and an owner for each status you intend to keep
- Split the waiting status into parts, permit, shutdown and engineering
- Brief supervisors and stores on the new definitions at the next toolbox talk
Work request standard and daily screening
Requests that say only 'pump leaking' cost the planner a site visit before anything can be planned, and duplicates fill the backlog. A short standard for what a request must contain, plus a daily screen by the planner and an operations lead, stops poor requests at the door and gets genuine emergencies to the supervisor at once.
First tasks
- Write the five fields every work request must contain
- Agree a fifteen-minute daily screening slot with the operations lead
- Screen new work requests with operations and approve, return or merge each @recurring(daily)
- Count returned requests at the end of each month and share the reasons
Maintenance priority matrix agreed with operations
When every job is marked urgent, the priority field means nothing and the loudest voice sets the schedule. A matrix that combines consequence (safety, environment, production, cost) with how soon the failure will bite gives four or five priority codes with target start times that operations and maintenance have both signed.
First tasks
- Pull last quarter's work orders and count them by priority code
- Draft consequence rows and time-to-impact columns for the matrix
- Hold a one-hour session with operations to agree target start times
- Re-code thirty open jobs against the signed matrix