Each project arrives with its purpose, milestones and first tasks written out. Here is how the first three read.
Gas supply contract position summary
Most rate cut arguments start because nobody on site can say quickly what the plant is entitled to, what it must pay for whether it takes it or not, and what the supplier may cut without penalty. A two-page summary of contracted daily quantities, take-or-pay terms, interruptibility and force majeure wording, prepared with the commercial team, gives engineers and managers the same starting point when supply tightens.
First tasks
- Ask the commercial team for the current gas sales agreement and amendments
- List contracted daily quantity, pressure and quality limits in one table
- Summarise the curtailment, take-or-pay and force majeure clauses in plain words
- Have the commercial lead check the summary before it is issued
- Check the summary against any new contract amendments @recurring(yearly)
Site gas consumption baseline by user
A plant that takes 120 MMscfd may use a third of it as fuel and the rest as feedstock, and those two streams behave very differently when supply is cut. Building a baseline of normal consumption for each major user, from reformers and gas turbines to boilers, flare pilots and fired heaters, shows where gas actually goes and which users have room to move.
First tasks
- Pull the site gas metering diagram and list every user it shows
- Export twelve months of hourly gas flow for each metered user
- Estimate unmetered users from design data and note the method
- Chart the fuel and feedstock split for the whole site
Minimum stable rate and turndown limits register
When the supplier asks how much gas the plant can give back, the honest answer depends on the lowest rate each train can hold without tripping, flaring or damaging equipment. A register of minimum stable rates, with the equipment that sets each limit (compressor surge, burner stability, reformer tube temperatures, catalyst limits), turns that answer from a guess into a documented number.
First tasks
- Find past periods of low-rate operation in the historian for each train
- Record the limiting equipment and reason for each minimum rate
- Check compressor and burner turndown against vendor data
- Hold a review with operations and rotating equipment to sign the register