Turnaround milestone timeline from T-24 months
Every well-run turnaround works backwards from the shutdown date along a published milestone timeline, often counted as T-24 months to T+3 months. Without one, scope arrives late, long-lead items miss the window and the plan is still being written when contractors arrive. Drawing the timeline first gives every later project a date to aim at and lets the steering group see slippage while it can still be fixed.
First tasks
- Confirm the target shutdown date and planned duration with operations
- List the milestones your site turnaround procedure requires
- Count back from the shutdown date to set a date for each milestone
- Assign an owner and a done definition to every milestone
- Issue the timeline to the steering group for endorsement